Stan Jessup's 'forty something' chief project - Part 2
Well, last month we laid the ground work for the new project Chief. The bike arrived quickly, and well packaged. The disassembly and inspection of the parts has begun, and some problems uncovered. When the seller was asked about
engine or case welds, there were none.... wrong! Both have had some repair work,
but both appear useable at this point. The engine was rebuilt 7 years ago, and
actually this part was true. However, the iron flywheels are very rusty, so
moisture has been present without protection. The heads are good, and have only
minor fin damage which I'll leave since this is a rider. Due to moisture,
disassembly is slow and painful, but we're making progress. The forks are poor,
but may be salvageable. The frame had nice paint, but from years of kicking
around in a basement, it will need to be repainted. The seat mount is missing
from the frame, so I would have messed up the paint anyway, when I re-weld a new
casting in place. The front wheel is correct for a front drive speedo, but the
hub is laced to an 18" rim. Generator needs a rebuild, the carb needs a
brass float (it's also an accessory model Linkert). Rear wheel will need
refinish and spokes, but otherwise looks solid. Of course most of the small bits
are missing, but the kicker arm and gears are all very nice. The transmission
internals look new, but we'll have to do some inspecting upon disassembly. All
of the shock parts are there, as well as the distributor and oil pump. The pump
is pretty rusty, so it will need a good soaking prior to disassembly. Engine cases
It turns out that the case welding is pretty solid, but whoever did the repairs never bothered to grind out any of the welds. The transmission internals are all new, so it was just a matter of stripping it down, clean it up, seal the inside, paint the outside, and reassemble. Typically, the "rebuilder" left out a few small pieces in the transmission, but it was never run, so no harm done. The engine internals were surprisingly clean, other than surface rust on the flywheels. They used some sort of assembly lube on the shafts and bearings that has since turned to bear snot, but it cleaned up to reveal brand new shafts and bearing races. It took a full can of Aerokroil to free up and disassemble the oil pump, but again everything (except the gears) is perfect.
Now it's time to get in the proper mind set to spend countless hours with the bead blast cabinet. This isn't too glamorous or fun, but it is a necessary evil. Remember to clean the parts very well after bead blasting to remove any embedded beads. I hate doing wheels, so as you may have noticed, I left these till last. Since I am only planning to use the original rear wheel, I'll leave the front alone for now. Once I removed the rear drum, inspection revealed that two of the stud holes had been re-threaded, and the sprocket was welded to the drum. Since removal of the welds would likely destroy an otherwise salvageable drum, I'll just clean them up and replace the remaining rivets. The bearing area of the drum is badly worn, but I can repair the wear enough to keep the ´ bearing from spinning which is welcome news. The rear rim will be powder coated, so it will go to the chrome shop first, for chrome removal.
I can't stress enough how expensive it will be to replace the missing parts in a basket case bike! Keep watching the cost sheet, as things start to escalate. When you are placing orders for small items that only cost $3 or $4 each, make sure to add up the totals before placing the order. These small items add up very fast, and you can easily underestimate how many of these "cheap" little widgets there are in an Indian. On this project, I am careful to salvage anything I can, except in critical areas that could cause catastrophic failure (fatal error for you tech heads). You may be able to clean a crusty old bearing up, and think it is perfect, but for the $20-40 (depending on which one), it really isn't worth destroying a $600 (or more) part when it fails. THROW THEM AWAY! If you decided to try reusing a transmission main bearing, and it fails, you could take out the Housing ($600), Main Shaft ($275), Clutch Basket ($150), for a total of $1025 worth of damage, not counting time, and assuming no other damage was done. Buy the cheaper, "replacement" head light if you need to save money, rather than skip the bearings....... Unfortunately, this project bike
was missing all of the seat components (seat pan, seat post, bushing, seat T,
and pivot mount) which will add a little over $500 to the project cost. These
are things that you want to take into account when negotiating with a seller.
Often the seller bought the bike in pieces some time back, with the dream of
putting together a real Indian motorcycle, and then realized that they either
couldn't afford to finish it, or they had no clue how to finish it. In this
case, they also have no clue what things cost today. Do the homework before you
buy a basket case so you are armed with enough information to negotiate a fair
deal. I see baskets advertised all the time for $7-9000, and if you pay the
price you will end up with a very expensive lesson in what parts cost when you
go to complete the bike. In this case, I'm into the basket for around $5000 with
shipping, so we have a bit more room to work, and still keep the cost within
reality. Since this is a Virtual Indian project topic bike, I decided early on, to use parts that were made by VI list members whenever I could. For a little extra crankcase ventilation, I bought a "new and improved" Moto Valve from Duffy (casting by Lyle), and it looks to be a very nicely made unit. Commercial dealers that have made VI aware of new products that I can use, will supply those parts so that I can evaluate the fit and function. All of the parts for this project are paid for, and not donated by any of the dealers. I will highlight the new parts as they are used, but I have no commercial interest in any of them. If they work, I'll say so. If they don't, I'll tell you that too, along with what I didn't like about the product, or what needs correction. I primarily use the 3 major parts dealers, and in this case, tried to split the orders up pretty equally, but that never works out perfectly, so when looking at the cost sheet, you should not assume that the dealer that sold me the most parts (read dollars), is necessarily my favorite, or a "preferred" dealer. Well, parts are starting to arrive, so I have work to do. Next month maybe I can supply some pictures of subassemblies that start to look more like a real motorcycle! Until then, Indian's rule, and Harley's drool! Pass the word.... |
|
Please support us with a paypal donation if you want the site to continue! |